Cindre

Efficiency On Point – Cindre’s 25-Day Mold Production Timeline

In the intricate realm of mold production, a meticulous timeline unfolds, ensuring precision from client consultation to final approval. Let’s break down the logical steps:

Day 1-2: Initiating Precision

The journey begins with a thorough consultation to confirm part specifications. Using CAD software on Day 2, a preliminary mold design takes shape. Specialized flow software predicts potential issues during the injection molding process.

Day 3: Fine-Tuning Design

Any identified issues are discussed with the client, adjustments are made, and the mold design is finalized.

Day 4: Materialization

The mold material is carefully chosen based on the part’s requirements.

Day 4: Materialization

The mold material is carefully chosen based on the part’s requirements.

Day 5-6: Material Procurement

Selected materials are procured from trusted suppliers.

Day 7: Raw Material Preparation

Preparation of raw material involves meticulous cleaning, pre-treatment, and defect checks.

Day 8-9: Precision Machining

CNC machines sculpt the mold’s cavity, core, and other components with precision.

Day 10: Seamless Assembly

Various mold components are assembled with a keen eye on perfect alignment.

Day 11: Efficient Cooling Implementation

Cooling systems, like water channels, are integrated for uniform cooling during injection molding.

Day 12: Preliminary Testing

A preliminary test ensures functionality and alignment.

Day 13-15: Surface Treatment

Polishing and treatment enhance part release, aesthetics, and mold durability.

Day 16-18: Quality Assurance & Refinements

Stringent tests identify defects, misalignments, or issues. Necessary refinements are made, culminating in a final quality check.

Day 19-21: Machine Integration

The mold is installed, machine settings are calibrated, and test cycles are run without injecting plastic.

Day 22: Sample Production

Sample parts are produced, setting the stage for meticulous inspection.

Day 23: Rigorous Inspection

Parts are scrutinized for accuracy, dimensions, aesthetics, and functionality.

Day 24: Adjustment and Perfection

Necessary adjustments to machine settings or the mold are made based on the sample review.

Day 25: Client Approval & Production Green Light

Sample parts are presented to the client for review and approval. Upon the client’s nod, the mold is primed for full-scale production.

This logical timeline offers a glimpse into the precision and dedication that define our mold production process. Note: Timelines may vary based on project complexity and material specifics.